Project Description
Two post tensioned, single span concrete deck structures
over the A64 dual carriageway were removed and replaced with
new twin span steel composite decks, including new central
columns. The existing abutments, bearing shelves and wing
walls were modified to accept the new decks. A temporary footbridge
was required for one of the bridges as this linked two sides
of the Fulford Golf Course. The existing decks were transported
to a temporary yard area, adjacent to the A64 in a field,
for demolition. The new decks were constructed in the same
yard, where they were jacked to their full height prior to
transportation.
Our Involvement
Birse Civil Engineering were assisted by Birse Technical
Services providing the temporary works design expertise at
tender and contract stages. Duncan Noble led the engineering
team on behalf of Birse Technical designing or approving all
the temporary works on the project. Halcrow designed the permanent
works for the project.
The temporary footbridge was provided by a sub-contractor
who also erected and dismantled the bridge. This bridge required
an Approval in Principle document which we contributed to
in order to ensure that the design elements were properly
described and approved by the Technical Approval Authority.
We also inspected and logged geotechnical trial pits to enable
the design of the reinforced concrete footbridge foundations
and designed steel guy wires to attached adjacent bridge foundations
and buried kentledge to resist lateral wind loading.
One of the critical items of the temporary works was the
protection of a high pressure sewerage rising main (pressurized
to 14 bar). This lay across the only access to the temporary
yard area which had to be crossed by the SPPTs carrying
a 400T bridge deck! We had to prove to the water authority
that the protection we designed would not load the pipe (900mm
below ground level) at all. Our solution was a reinforced
concrete slab cast on strip footings each side of the main.
The slab was cast on clayboard void former under
the slab which was subsequently wetted through holes in the
slab to ensure a clear void between the slab and the main
to allow any settlement under load without affecting the main.
The geotechnical aspects of the temporary works were critical
to the overall success of the project as many of the temporary
works schemes had a geotechnical basis. The large yard area
required extensive treatment to enable the SPPTs to
operate. The high applied loads, stringent settlement limits
and consequences of failure made the assessment a high risk
issue for both cost and operational criteria. Duncan Noble
assessed the geotechnical report and devised a suitable, cost
effective scheme, then personally monitored the preparation
of the sand bearing stratum and temporary stone mat, advising
the site team on the suitability of clay pockets in the formation
and soft areas. We commissioned and analysed plate bearing
tests of the finished yard to ensure that the bearing assessments
were valid and induced settlements would not be excessive.
We carried out an extensive route/configuration planning
exercise for the SPPTs to limit costly temporary highway
widening, eventually settling on a double trailer unit under
each deck and a diagonal configuration whist running on the
highway. In addition to limiting the highway widening this
also reduced costly crash barrier removal. As part of the
assessment we carried out structural analysis to ensure the
existing post tensioned decks, of poor quality, could withstand
the long cantilevers beyond each temporary support position.
We also designed temporary concrete walls to support the new
decks during construction, after our cost exercise found that
this solution was cheaper than using proprietary steel trestling.
Our innovative falsework solution to the deck edges allowed
the deck to settle under concrete loads (ie removing some
pre-camber) whilst being supported by simple acaffolding from
the ground.
The project was very successful, all possession work was
completed as planned and the contract was delivered on time
and to budget.
|