Project Description
This project comprises of 20 large wind turbines, each capable
of producing 2.5MW of power with an overall height of 100m.
Birse Process was awarded the EPC contract to design and build
all the civil engineering, building and electrical works on
the project. The German company, Nordex, then erected their
turbines on completed foundations and connected into the electrical
system. In order to deliver the large, heavy turbine components
a number of detailed modifications were needed to the public
highway and a new 6km access track was constructed along the
remote hillside to Crystal Rig site. A new 33kV substation
was built at the grid connection point near Dunbar and a larger
control building was built on site. Birse Process installed
an 11km HV underground cable connection over the hills between
the two buildings. Large reinforced concrete turbine and anemometer
foundations were constructed using a concrete batching plant
on site.
Our Involvement
Birse Process Engineering won this contract against a very
competitive field of contractors. With the help of Birse Technical
Services the submitted bid was of very high quality and demonstrated
how we proposed to overcome the considerable civil engineering
challenges of constructing massive turbines in a high, remote
environment. Duncan Noble led the engineering team on behalf
of Birse Technical designing much of the tender and contract
stage works without using external provision, and was responsible
for schedule and cost management of the design works.
Birse Technical Services were responsible for the design
of all the civils permanent works on the project. The extensive
site tracks and highway modifications required a detailed
knowledge of how the massive components for the turbines were
to be transported and erected. This was a challenge which
had to be done in an environmentally sensitive location high
in the Scottish Borders. Each blade is 40m long and transported
as a single load from Germany, thats approximately 3
times longer than a standard UK trailer.
The turbine foundation design was carried out by a specialist
consultant on behalf of Technical Services. Together we endeavoured
to find the most efficient possible foundation solution. Even
a small volume of reinforced concrete designed out of each
base can multiply into considerable savings over the whole
wind farm, concrete works carried out on a Scottish mountain
are not cheap! We carried out a significant value engineering
exercise on all aspects of the base, in particular the holding
down bolt arrangement and overall concrete volume, to provide
a very efficient and effective design. Each turbine base has
an individual drainage system, which links into the network
of drainage channels on site, designed to control buoyancy
effects on the gravity bases.
The cranes used to erect the turbines were among the largest
crawler cranes available in Europe. We designed the yard areas
to accommodate the bearing pressures from these giant cranes,
using site won stone.
We also designed the control building on-site and the substation
off-site at the grid connection point, some 11km from the
site. These buildings need to withstand very harsh weather
conditions and house sensitive control equipment.
By working closely and cooperatively with many specialist
advisors we were able to provide Birse Process and the Client
with a high degree of support on site. The wind farm is now
fully operational and the Client regularly exports the full
50MW capacity to the national grid.
|